Eolico onshore
Murtomäki
Pyhäjärvi, Finlandia
- Fase
- In operazione
- Comune
- Pyhäjärvi
- Data di inizio
- 2023
- Produzione
- ~ 300 GWh
A proposito del progetto
The Murtomäki wind farm is located in the town of Pyhäjärvi in Northern Ostrobothnia, Finland.
The wind farm consists of 15 wind turbines with a total rated power of approximately 93 MW and an estimated annual production of approximately 300 GWh, which is equivalent to the annual electricity consumption of 60,000 households (5,000 kWh/household).
The wind farm is connected to Elenia's 110 kilovolt electricity grid.
The Murtomäki wind farm was constructed during 2022 and 2023. OX2 has been responsible for the technical and commercial management of the wind farm since late 2023. The wind farm is owned by Ålandsbanken Wind Power Fund Non-UCITS.
Murtomäki is one of the wind farms implemented by a third party and managed by OX2.
Più informazioni sul progetto sono disponibili sul sito Finlandese Svedese e Finlandese
Dati di progetto
- Tecnologia
- Eolico onshore
- Fase
- In operazione
- Comune
- Pyhäjärvi
- Turbine
- 15
- Altezza
- 247 m
- Data di inizio
- 2023
- Produzione
- ~ 300 GWh
- Proprietario
- Ålandsbanken Tuulivoima Erikoissijoitusrahasto
- Fornitore
- Vestas
- Gestito da
- OX2
Hankkeen uutisia
2022
OX2 hallinnoimaan Murtomäen tuulipuistoa
Vuoi saperne di più?
Contatti del progetto Murtomäki
Commercial asset manager
Taru Kaarlela
+358 40 623 3995
taru.kaarlela@ox2.com