Pohjasuo

Mikkeli, Finland

Phase
Under development
Location
Mikkeli
Production
77,5 GWh
Capacity
80 MW

About the project

The Pohjasuo solar power project is located in the municipality of Mikkeli Etelä-Savo region, Finland.

The planned capacity of the project is 80 MW. Once completed, the annual energy production of the solar farm is estimated to be approximately 77,5 GWh, which corresponds to the annual electricity consumption of almost 15,000 households (5,000 KWh per household).

What's next?

A start has been made on the technical design of the project. An environmental survey of the area of influence of the project will be prepared in 2023 and 2024 to thoroughly study the impacts of the project on the environment. If needed, an environmental impact assessment (EIA) will also be carried out in the project. The Centre for Economic Development, Transport and the Environment (ELY Centre) is responsible for the EIA needs assessment.

The aim is to have the investment decision to build the project by the end of 2026 and for construction work to begin in the same year. The solar power farm is estimated to start operating in 2029.

Key facts

Project key facts

Technology
Solar energy
Phase
Under development
Location
Mikkeli
Production
77,5 GWh
Capacity
80 MW

Kysymyksiä ja vastauksia aurinkovoimasta

Mitä tarkoittaa teollisen mittakaavan aurinkovoimala? Mitä hyötyä suurista aurinkovoimahankkeista on? Mikä on aurinkovoimalan käyttöikä? Näihin ja moneen muuhun kysymykseen löydät vastaukset koostamastamme materiaalista.

Tutustu kysymyksiin ja vastauksiin

Do you want to know more?

Project contacts for Pohjasuo

Project manager
Saku-Matti Mäki

+358 40 752 7045
saku-matti.maki@​ox2.com

Land use manager
Isra Alatalo

+358 40 770 9958
isra.alatalo@​ox2.com