Logotype

Landbaserad vindkraft

Dobrzyca

Dobrzyca, Polen

Fas
Driftsfas
Plats
Dobrzyca
Driftstart
2021
Produktion
189,8 GWh

Om projektet

The Dobrzyca wind farm is located on the area of Dobrzyca commune, Jarocin county, Greater Poland voivodeship, approximately 88 km from Poznań. The wind farm consists of 19 wind turbines G126 with a total capacity of 49.9 MW. The expected annual electricity production is 189,8 GWh, which corresponds to the yearly electricity demand for 58 thousand households.

This is an externally developed and constructed wind farm for which OX2 provides technical and commercial management services.

Feel free to contact us about the project Dobrzyca:

Anna Bulewicz 

anna.bulewicz@ox2.com  

+48 573 435 698

Mer information om projektet finns på den polska sajten, på polska

Nyckelfakta

Projektets nyckelfakta

Teknologi
Landbaserad vindkraft
Fas
Driftsfas
Plats
Dobrzyca
Antal turbiner
19
Höjd
137 m
Driftstart
2021
Produktion
189,8 GWh
Ägare
Orlen Wind 3, Grupa Orlen