Skip to main contentSkip to navigationSkip to search
Logotype
Rendering of offshore wind turbines in calm sea, with a large turbine hub in the foreground and three more in the distance.

Offshore wind power

Galene

Kattegatt, outside the coast of Halland, Sweden

Phase
Under­ development
Location
Kattegatt, outside the coast of Halland
Area
Sweden's Exclusive Economic Zone
Production
1,7 TWh
Capacity
400 MW

Strengthening southern Sweden's power supply

The Galene offshore wind project is located in the Kattegat, 22 km off the coast of Varberg in Halland County. The wind farm is expected to generate approximately 1.7 TWh of electricity annually, corresponding to the electricity consumption of around 320,000 households. A substantial increase in renewable electricity generation is required to enable the green transition. Sweden has significant potential for offshore wind power, and there is a growing need to expand electricity production, particularly in southern Sweden.

In partnership with Ingka Investments

OX2 is developing Galene together with Ingka Investments, part of the IKEA Group, which is a co-owner of the project. Ingka Investments is a long-term investor with ambitious climate targets. The company invests heavily in renewable energy generation and today owns more than 2 GW of renewable energy capacity. 

Key facts

Project key facts

Technology
Offshore wind power
Phase
Under­ development
Location
Kattegatt, outside the coast of Halland
Area
Sweden's Exclusive Economic Zone
Number of turbines
21
Height
Max 340 m
Production
1,7 TWh
Capacity
400 MW
Price area
SE3
Owner
Ingka Investment 49%, OX2 51%

What's next?

Galene has now obtained all the main permits required to move the project forward, as outlined further down this page. What remains is the need for stable, long-term market conditions that can support investment in new offshore wind capacity. Once these long-term conditions are in place, the ambition is to begin construction as soon as possible. From a final investment decision, it takes approximately three years before the offshore wind farm can begin delivering electricity to the grid.

Galene enables large-scale seaweed farming

OX2 has signed letters of intent with the companies Swedish Kelp and Nordic Seafarm to explore opportunities for large-scale seaweed cultivation within the Galene offshore wind farm. Seaweed farming can improve the marine environment by absorbing nitrogen, phosphorus and carbon dioxide, while also creating new habitats for fish. In addition to contributing to a healthier marine ecosystem, the initiative could support the development of a new sustainable industry and create additional jobs in the region over time.

Sweden needs offshore wind power

Sweden, like the rest of the world, must under­take major changes to mitigate the effects of climate change. The electrification of industry and transport is widely recognized as one of the most important measures to achieve this transition. At the same time, the changing security situation in Europe has highlighted the importance of reducing dependence on imported energy. As Sweden's electricity system is interconnected with the rest of Europe, Swedish consumers and businesses are also affected by high electricity prices elsewhere in the region. Taken together, the need for additional domestic electricity generation in Sweden is both significant and urgent.

Timeline of permits obtained

May 2023 – The Swedish Government granted Galene a permit under­ the Swedish Exclusive Economic Zone Act (EEZ Act). The decision was appealed to the Supreme Administrative Court, which on 3 February 2025 rejected the appeals and upheld the Government's decision.

July 2024 – The Land and Environment Court granted Galene a permit under­ Chapter 7, Section 28a of the Swedish Environmental Code relating to impacts on nearby Natura 2000 areas. An earlier permit issued by the County Administrative Board of Halland in January 2023 had been appealed to the Court. The Court's ruling in July 2024 largely confirmed the original decision.

November 2024 – The Land and Environment Court granted Galene a permit under­ Chapter 11 of the Swedish Environmental Code to install up to five submarine cable systems for electricity transmission within the project area.

April 2025 – The Swedish Energy Markets Inspectorate (Ei) granted a network concession for a combined offshore and onshore power cable from Sweden's territorial boundary in the Kattegat to the grid connection point at Värö Peninsula in the Municipality of Varberg. The decision was appealed to the Land and Environment Court of Appeal. In October 2026, the Court confirmed that the permit had gained legal force.

June 2025 – The Swedish Government issued a permit under­ the Continental Shelf Act for the installation of subsea cables within the wind farm, as well as from Sweden's Exclusive Economic Zone to Sweden's territorial boundary and through territorial waters for connection to the Swedish mainland. 

Pebble beach and sea with a distant row of offshore wind turbines on the horizon under a pale blue sky.

Visualiseringar

Fotomontage finns tillgängliga från flera utkikspunkter längs Hallandskusten. På bilden visas ett fotomontage från Glommen Glomstenen.

Visualiseringar [pdf]

Our responsibility

Do you want to know more?

General inquiries
[email protected]

Project contacts for Galene

Project manager
Matilda Hagert

+46101863040
matilda.hagert@​ox2.com

Matilda Hagert


Lise Toll

+46 76 109 59 33
lise.toll@​ox2.com

Lise Toll